5. The licensee of a geophysical survey must, while the survey is being carried out, send a weekly written report of activities to the Minister on the form prescribed in Schedule IA.
In accordance with the instructions of the geophysical survey licensee, the operator may submit the report.
The weekly report must include:(1) the geophysical survey licence number;
(2) the period covered;
(3) the licensee’s name;
(4) the number of kilometres of lines of the geophysical survey covered during the period and the number remaining;
(5) the dates of the start-up, interruptions, resumptions and completion of operations;
(6) the length of interruptions of operations due to weather conditions, breakdowns and technical difficulties;
(7) the location and number of lines of the geophysical survey to be covered during the following period;
(8) the last location of the ship, if applicable.
O.C. 1539-88, s. 5; O.C. 1381-2009, s. 5.